Reconstruction of the Water Supply System — Yangiyul
Yangiyul City · 2022–2024 · General contractor
Project data
- Contract value
- $5.59M
- Status
- Completed
- Years
- 2022–2024
- Role
- General contractor
- Region
- Yangiyul City
- Client
- Medium-Size Cities Integrated Urban Development PIU, Ministry of Economy and Finance
- Funder
- World Bank (IBRD)
- Contract No.
- MSC-Y/W/1.2
- Value in UZS
- 60 836 956 408 UZS
Description
Reconstruction of the water supply system in Yangiyul city under contract MSC-Y/W/1.2. Delivered as general contractor for the Medium-Size Cities Integrated Urban Development Project Implementation Unit of the Ministry of Economy and Finance.
Scope of work
- City-wide distribution network reconstruction
- Pump stations and storage
- Service connections